1、The environmental assessment report of the project was made in June 2015, and the project was approved by the Management Committee of the Development Zone on August 18, 2015, with a total construction area of 17763 square meters and a five storey concrete frame structure above the ground.

2、On February 23, 2016, the planning license of Nanjing Municipal Planning Bureau was obtained. On October 27, 2016, the construction license was completed, and the construction began in the same month.

3、On May 16, 2017, all the main works were completed.

4、Indoor water and electricity installation and fire protection system commissioning were officially completed in August 2018. The total construction period of the project is 660 days.

5、In April 2019, the completion acceptance of the main body of the plant was put on record. In June of the same year, the environmental protection acceptance of the plant was completed.

6、On November 6, 2019, the real estate registration was completed.


20200623070143_62054.png +86 25 85805799

20200623070212_45519.png +86 25 84490322

20200623070157_38040.png [email protected]


Copyright © 2020 Nanjing Hong An Medical Appliance Co., Ltd.,All rights reserved.